请问有谁的公司用XP PROGRAMMNG开发系统?

[复制链接]
kiwifruit 该用户已被删除
发表于 9-5-2006 11:09 AM | 显示全部楼层 |阅读模式
请问有谁的公司用XP PROGRAMMNG开发系统?
回复

使用道具 举报


ADVERTISEMENT

joe216 该用户已被删除
发表于 9-5-2006 11:39 AM | 显示全部楼层
我很笨。。。什么是 XP Programmng?
回复

使用道具 举报

kiwifruit 该用户已被删除
 楼主| 发表于 9-5-2006 11:50 AM | 显示全部楼层
XP programming, a methodology approach for developing software. It exist b4 i born, 80 centurt sth kind.

instead of SDLC, XP progamming is one of the agile methodology to developing software.empahasize on code as documentation. instaed of using SDLC, (requirement->design->coding->testing) in the whole cycle, XP will to it iteratively, the activity will split in many iteration, every iteration doing 3 to 4 week, every iteration will do (requirement->design->coding->testing), like spiral model.
回复

使用道具 举报

发表于 9-5-2006 03:43 PM | 显示全部楼层
。。。我还是不懂楼主讲什么。
回复

使用道具 举报

kiwifruit 该用户已被删除
 楼主| 发表于 9-5-2006 04:09 PM | 显示全部楼层
哈哈, 抱歉。。。

SDLC (SOFTWARE DEVELOPMENT LIFE CYCLE)is a waterfall approach, first requirement, then analysis, then design, coding then testing, then finish (got final product).

XP programming, a type agile methodology, like a spiral model, split the whole deveolpment process in some iteration, each iteration will be 3 - 4 week, every iteration will do all the process in the whole waterfall cycle (analysis, design, coding, and tesing) for some module, if cannot finish, function will be cut or finish at another iteration.

so compare to SDLC, at least can c some product at first, (imaging u write a super high end programmer , then after that, u find that this is not what customer want...this is one of the weakness of SDLC).

agile methodlogy like XP is more embrace CHANGE.
回复

使用道具 举报

发表于 9-5-2006 04:37 PM | 显示全部楼层
是不是tranditional life cycle?
example:
(phase 1=analysis) analysis-->design-->develop-->testing
(phase 2=design) design-->develop-->testing-->analysis
(phase 3=develop) develop-->testing-->analysis-->design
(phase 4=testing) testing-->analysis-->design-->develop
keep looping,when analysis phase,also do design,develop n testing,but the only different is time alocation
回复

使用道具 举报

Follow Us
kiwifruit 该用户已被删除
 楼主| 发表于 9-5-2006 04:46 PM | 显示全部楼层
no no no...like this

iteration 1 (analysis-->design-->develop-->testing) -3-4 weeks (jan) (module A)
iteration 2 (analysis-->design-->develop-->testing) -3-4 weeks (feb) (module B)
iteration 3 (analysis-->design-->develop-->testing) -3-4 weeks (mar) (module B) if module b to large...then shift to iteration 3.
...etc.

but will do a sketch of the overall system, XP will do the 'spike'(the most critical module) first
回复

使用道具 举报

发表于 9-5-2006 05:05 PM | 显示全部楼层
我想楼主说的是
eXtreme Programming吧。
http://en.wikipedia.org/wiki/Extreme_Programming

本地应该很少(还没听说有)公司用吧。
是一种比较近与Agile Software Method / Modelling.和传统的SDLC有很大不同,
主要重于灵活性。

我也是一知半解。很久前在某网站的Articles和ebook看过。

参考资料:
http://www.itcomputer.com.cn/Programs/Java/java/200512/2912.html

[ 本帖最后由 extrem23 于 9-5-2006 05:09 PM 编辑 ]
回复

使用道具 举报


ADVERTISEMENT

kiwifruit 该用户已被删除
 楼主| 发表于 9-5-2006 05:10 PM | 显示全部楼层
yes yes yes....eXtream programming...
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

 

ADVERTISEMENT



ADVERTISEMENT



ADVERTISEMENT

ADVERTISEMENT


版权所有 © 1996-2023 Cari Internet Sdn Bhd (483575-W)|IPSERVERONE 提供云主机|广告刊登|关于我们|私隐权|免控|投诉|联络|脸书|佳礼资讯网

GMT+8, 22-9-2024 03:41 PM , Processed in 0.105813 second(s), 26 queries , Gzip On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表