A)Interlooking Steel Piles
1) Bringing in & removing plant - Item
2) MAintain plant on site- Item
Permanent Piles
3) Total area of piles - m2
4) Total driven area - m2
5) Corner piles - No
6) Cut Piles to form holes - No
7) Cut off piles heads - m
Piles to be extracted
8) Total area of Piles - m2
9) Total Driven area - m2
B)Site Clearance
Alternative 1
1) Clearing undergrowth - m2
2) Cutting down trees( n.e. 300, 300-600, 600-900.... gth) - No
3) Cutting down hedges - m
Alternative 2
1 ) Site Clearance - m2
C)Frame
1) Concrete for column - m3
2) Formwork for column - m2
3) Reinforcement bars for column - m ( then change to kg)
4) LInks for Column - m ( then change to kg)
5) Concrete for Beam - m3
6) Formwork for Beam - m2
7) Reinforcement bars for Beam - m ( then change to kg)
8) Stirrups for Beam - m ( then change to kg)
[ 本帖最后由 darnell 于 30-11-2005 07:48 PM 编辑 ] |
|
|
|
|
|
|
|
发表于 30-11-2005 08:32 PM
|
显示全部楼层
|
|
|
|
|
|
|
发表于 1-12-2005 04:23 PM
|
显示全部楼层
谢谢!感激不尽!!现在有些还没用到所以不是很明白。。。谢谢。。 |
|
|
|
|
|
|
|

楼主 |
发表于 1-12-2005 08:58 PM
|
显示全部楼层
原帖由 Atila02 于 30-11-2005 08:32 PM 发表
楼主乐于助人,值得嘉许,加油。
谢谢捧场哦...
嘻....
原帖由 wo_pui 于 1-12-2005 04:23 PM 发表
谢谢!感激不尽!!现在有些还没用到所以不是很明白。。。谢谢。。
我会的不是很多,但我会尽量分享我会的...希望能帮到你.....有错的话,请大家纠正我....
也希大家能一起讨论... |
|
|
|
|
|
|
|

楼主 |
发表于 1-12-2005 09:31 PM
|
显示全部楼层
Suspended Floor
1) Concrete for Floor Slab - m3
2) Formwork work for floor slab - m2
3) Fabric ( m2) or reinforcement bar (m) for floor slab - (change to Kg)
Internal Wall
1) Half brick (around 115mm) wall - m2
2) waterproofing - m
3) Concrete for stiffener - m3
4) Formwork for stiffener - m2
5) Reinforcement bar for stiiffener -m (change to Kg)
External Wall
1) One Brick wall (around 230mm) - m2
2) waterproofing - m |
|
|
|
|
|
|
|

楼主 |
发表于 3-12-2005 06:09 PM
|
显示全部楼层
Internal Floor Finishes
1) Cement Render- m2
2) Screed for carpet - m2
3) Underlay - m2
4) Carpet - m2
5) Sceed for Ceramic tiles -m2
6) Ceramic tiles - m2
7) Sceed for Marble -m2
8) Marble - m2
9) Sceed for Skirting - m
10) Skirting - m
11) Devidind strip - m |
|
|
|
|
|
|
|
发表于 18-11-2006 01:08 AM
|
显示全部楼层
楼主,这些我都有了。
请问又谁有其他的呢?
比如说 piling, basement or others... |
|
|
|
|
|
|
|
发表于 18-11-2006 07:57 AM
|
显示全部楼层
Piling
Pad Footing
1. Excavation top soil - m2
2. Excavation to reduce level - m3
3. Excavation pit for pad foundation - m3
4. Extra over-in rock excavation - m3
Footing
5. Lean Concrete - m3
6. Concrete in pad footing - m3
7. Formwork for pad footing - m
8 rebar in pad footing - m/kg |
|
|
|
|
|
|
|
发表于 18-11-2006 08:03 AM
|
显示全部楼层
ROOF STRUCTURE
1. wall plate - m
2.rafter
a.common rafter - m
b.hip rafter - m
c.valley rafter - m
d.jack rafter - m
e.crown rafter - m
3.ridge board - m
4.batten - m
5.ceiling joints - m
ROOF COVERING
1.roof tile - m2
2.hip tile - m
3.ridge cap - m
4.flashing - m
5.verge tiles - m
6.apex tiles - no
7.fair ends - no
8.insulation - m2
FASCIA BOARD
1.fascia board - m
RAINWATER INSTALLATION
1.RWDP - m
2.gutter - m
3.RW outlet - no
PAINTING
1.painting to fascia board - m
[ 本帖最后由 clementssl 于 18-11-2006 08:10 AM 编辑 ] |
|
|
|
|
|
|
|
发表于 4-3-2007 12:51 AM
|
显示全部楼层
菜 鸟 要 去 实 习 ! ! 各 方 朋 友 有 什 么 高 见 ? !
大 家 好 ! ! 小 妹 是 菜 鸟 ! 明 天 要 去 实 习 三 个 月 了 , 好 害 怕 也 ! 小 妹 是 学 院 文 凭 生 , 两 年 课 程 我 只 读 了 两 个 学 期 就 要 去 实 习 了 , 因 为 我 是 拿 stpm成 绩 去 报 这 课 程 的 。 所 以 还 有 很 多 很 多 不 会 的 地 方 。 。 大 家 有 什 么 高 见 吗 ? 有 什 么 需 要 特 别 注 意 的 地 方 去 实 习 的 时 候 ? ? 谢 谢 |
|
|
|
|
|
|
|
发表于 5-3-2007 08:22 PM
|
显示全部楼层
读书时有用到taking-off list
工作就没有必要 特别是contractor的
那些quantity都用Microsoft excel或其他的software(我不懂)
key in那些table(如有)就可以找到了 |
|
|
|
|
|
|
|
发表于 1-7-2007 06:25 PM
|
显示全部楼层
你知道T10的kg是多少吗?
那个formula你会吗?
我忘了那个formula |
|
|
|
|
|
|
|

楼主 |
发表于 5-7-2007 07:19 PM
|
显示全部楼层
原帖由 shs_sue 于 1-7-2007 06:25 PM 发表 
你知道T10的kg是多少吗?
那个formula你会吗?
我忘了那个formula
你要的是Unit Weight (kg/m)?
Y10 是0.616 |
评分
-
查看全部评分
|
|
|
|
|
|
|
发表于 5-8-2007 09:08 AM
|
显示全部楼层
steel density = 7850 Kg/m3, 不管什么尺寸,算出体集(volumn) 就能算出重量! |
|
|
|
|
|
|
|
发表于 15-7-2008 09:07 PM
|
显示全部楼层
T6 =
T8 =
T 10=
T 12 =
Fomula = (x^2/10^2) x 0.6174
For Example
T6 = (36/100) x 0.6174
= 0.222 kg/m
T8 = (64/100) x 0.6174
= 0.395 kg/m |
评分
-
查看全部评分
|
|
|
|
|
|
|
发表于 15-7-2008 11:06 PM
|
显示全部楼层
|
|
|
|
|
|
|
发表于 17-7-2008 03:07 PM
|
显示全部楼层
算rebar的conversion rate我也是用mamiko的formula的。。不过我是记 T12 = 0.888kg/m
不过如果是算structural steel, 7850这个数目还真的很重要。。 |
|
|
|
|
|
|
|
发表于 29-11-2009 11:09 PM
|
显示全部楼层
惨!!我太久没有taking off 了!!
很怕换公司会忘光光!! |
|
|
|
|
|
|
|
发表于 30-11-2009 10:02 AM
|
显示全部楼层
这里有人用其他SOFTWARE(不是EXCEL)来TAKING OFF吗?
听说有些软件可以直接EXTRACT QUANTITIES FROM AR & ST DRAWING的哦? |
|
|
|
|
|
|
|
发表于 1-12-2009 12:04 PM
|
显示全部楼层
原帖由 darnell 于 30-11-2005 07:42 PM 发表 
6) Cut Piles to form holes - No
7) Cut off piles heads - m
这两个有什么分别?为什么一个是No, 另一个是m?
谢谢指教。。。 |
|
|
|
|
|
|
| |
本周最热论坛帖子
|