jackykhoo77 发表于 20-9-2013 05:56 PM 
是material on site ?
那剩下的32.5是upon completion?
是material on site ?
那剩下的32.5是upon completion?
有没有给performance bond?
对,是指material on site,大多数只给75%,然后还要10%retention,所以只剩下67.5%而已...
例子如下
Material On Site: 20 ton rebar x RM2,000 / ton = RM40,000
Certify 75%: RM40,000 x 75% = RM30,000
Summary
Workdone: RM 20,000
Material On site: RM30,000
Total: RM50,000
Retention (10%): - RM5,000
Total : RM45,000
Material On Site只是要给你material的钱,帮助你的cash flow罢了,过后你也是拿那些piling去打桩啊...那时候你是claim workdone不是claim material on site了...
performance bond是subject to contract的,有些client如果看到contract amount太小可能不需要,不过多数都要,不然就从payment里面扣performance bond出来~~~
有错请shoot~~~
|