如果每次都那么长的process, sub con 可惨了,main con 通常不需要等sub con submit claim 才submit 上client 吧。sub con submit claim 的时间和main con submit claim 给client 的时间应该是不需要顺序的, main con 看到progress 了,要submit 就submit, 要不然
1. sub con 1/1/08 submit claim,
2. main con process one week ( 如果多project 的话不可能立刻process) , 改了, check 了,submit 给 client,
3. client 再process 多1-2 week , ( 有时候东西/figure 错了,item 错了, site agent verified 不到, site agent 忙/delay/等茶钱/appointment to site mearesument with qs。。。。。。)client process 好了再等main con 送去consultant 那里,(不一定是architect) ,
4. consultant 忙, delay 1-2 week, 再出cert ,
等client 搜到cert 都1-2天后,才process 去 account department, procedure 拉 一大堆的。
5. account 搜到后如果慢了,过了那个月的budget dateline, 要下个月才made payment, next month main con 拿到支票,才excercise payment 给 sub con 的话, 我看 sub con 跳楼了。。。。。。。。我看受到钱都1/4/08 了。
so the whole process shouldn't be like wat u mention b4, maincon should submit their claim base on their progress, shouldn't wait till recieved sub con only they excercise the claim to client, 但是我在developer, 我不肯定subcon 和 main con 的claim 是不是这样的。专家快快来解答。。。。。。 ![](static/image/smiley/default/loveliness.gif) |
|